United Technologies Services, Inc.
New York City · NYCHA PACT

Low-voltage infrastructure for occupied NYCHA rehabilitation projects.

United Technologies Services Inc. (UTECH) has delivered network and low-voltage scope on numerous NYCHA PACT developments across Manhattan and the Bronx — building the cabling, risers and in-unit systems residents depend on, while working around the families who live there every day.

5+ PACT Developments built
Manhattan & the Bronx
OSHA 30 · SST-10
Credentialed field crews
Certified Payroll & Davis-Bacon Compliant
submitted by Elation Systems or DOL Form WH-347
Project Experience

NYCHA Project Experience

Every project below was a full MDU build-out: core scanning and drilling, pipe-box riser construction, cabling into every unit, CPE and access point installation, rooftop antenna work, and final turn-up and activation. All of it was done during active renovation, alongside some of the city's most active PACT development and construction teams.

Frederick E. Samuel Apartments

  • Harlem, Manhattan
  • 40 buildings
  • 664 units
  • Full MDU build-out across a 40-building campus
  • In-unit CPE / AP and intercom installs
  • Coordination with the network vendor and security integrator
  • Documented repair of vandalism and cable-cut damage

Metro North Plaza & Gaylord White Houses

  • East Harlem, Manhattan
  • 4 buildings
  • 523 apartments
  • Full MDU build-out, every unit
  • Core scanning, core drilling and pipe-box risers
  • In-unit cabling with CPE / AP installation
  • Rooftop antenna scope through turn-up and activation

Boston Secor, Boston Road Plaza & Middletown Plaza (BBM)

  • Northeast Bronx
  • 3 developments
  • ~1,600 residents
  • Full MDU build-out across three developments
  • Core scanning, core drilling and pipe-box risers
  • In-unit cabling with CPE / AP installation
  • Rooftop antenna scope through turn-up and activation

Northwest Bronx Scattered Sites

  • Bronx
  • 14 buildings
  • 1,669 apartments
  • Full MDU build-out across mid-rise, high-rise and walk-up buildings
  • Hallway and in-unit surface raceway where walls could not be fished
  • Rooftop conduit pathways and antenna scope
  • Building-by-building install schedule coordinated with resident notices
Delivery & Compliance

What It Takes to Deliver Low Voltage on a NYCHA Rehab

A PACT gut rehab isn't a typical commercial job. The buildings are decades old, most units stay occupied, and compliance requirements reach well past the work itself. Here's what we plan for on every project.

01

Payroll & Compliance Paperwork

Certified Payroll & Davis-Bacon Compliant, submitted by Elation Systems or DOL Form WH-347. Weekly certified payroll and Section 3 reporting are prepared in-house. The GC and PACT partner never have to chase us for documentation.

02

Credentialed Crews

Field staff carry OSHA 30 and SST-10 credentials.

03

Working in Occupied Homes

  • Install days grouped by building so management can issue resident notices in advance
  • Tracking refused, no-access and “units to avoid” lists, with return visits scheduled
  • Daily unit-by-unit reporting so owners know exactly what’s done
04

Pathways in Older Buildings

  • Surface molding and raceway where masonry walls can’t be fished
  • Riser coring with GPR scanning, plus rooftop conduit pathways
  • Molding samples and mock-up units approved before full rollout
05

Many Stakeholders, One Schedule

PACT partner, GC, property management, ISP network vendor and security integrator all touch the same risers and IDFs. We coordinate pathways, rack space and device counts so trades aren’t working against each other.

06

Protecting the Work

Cable cuts and vandalism happen in occupied buildings. We log every incident, repair it, and document it through change orders — then test, label and certify everything at closeout.

Scope

Full MDU Build-Out, Start to Finish

One crew, one contract, from the first core to a live connection in every apartment.

  1. 01Core scanning (GPR)
  2. 02Core drilling
  3. 03Pipe-box riser build
  4. 04OSP / ISP Fiber installation and splicing
  5. 05Cabling into every unit
  6. 06CPE / AP installation
  7. 07Rooftop antenna scope
  8. 08Turn-up & activation
NYCHA PACT

Bidding a PACT Development?

Bring UTECH in early. We'll walk the buildings, flag pathway and access issues before they hit your schedule, and price the low-voltage scope accurately.

Contact UTECH